Title: RESEARCH ON RISK IDENTIFICATION AND COUNTERMEASURES
OF WATER RESOURCES SURVEY AND DESIGN ENTERPRISES
PARTICIPATING IN PPP PROJECTS
Authors: Bo Liu, Ming Che, You-you Duan, Shuai-jun Li, Yu Chen
|| ||
1Bo Liu, 2Ming Che, 3You-you Duan, 4Shuai-jun Li, 5Yu Chen
1. Lecture, Ginling College, Nanjing Normal University, Nanjing.
2,3,4,5. Postgraduate, Ginling College, Nanjing Normal University, Nanjing.
MLA 8 Liu, Bo, et al. "RESEARCH ON RISK IDENTIFICATION AND COUNTERMEASURES OF WATER RESOURCES SURVEY AND DESIGN ENTERPRISES PARTICIPATING IN PPP PROJECTS." Int. j. of Social Science and Economic Research, vol. 5, no. 2, Feb. 2020, pp. 320-333, ijsser.org/more2020.php?id=22. Accessed Feb. 2020.
APA(6) Liu, B., Che, M., Duan, Y., Li, S., & Chen, Y. (2020, February). RESEARCH ON RISK IDENTIFICATION AND COUNTERMEASURES OF WATER RESOURCES SURVEY AND DESIGN ENTERPRISES PARTICIPATING IN PPP PROJECTS. Int. j. of Social Science and Economic Research, 5(2), 320-333. Retrieved from ijsser.org/more2020.php?id=22
Chicago Liu, Bo, Ming Che, You-you Duan, Shuai-jun Li, and Yu Chen. "RESEARCH ON RISK IDENTIFICATION AND COUNTERMEASURES OF WATER RESOURCES SURVEY AND DESIGN ENTERPRISES PARTICIPATING IN PPP PROJECTS." Int. j. of Social Science and Economic Research 5, no. 2 (February 2020), 320-333. Accessed February, 2020. ijsser.org/more2020.php?id=22.
References [1]. Andreas Wibowo, Hans Wilhelm Alfen. "Identifying Macro-environmental Critical Success Factors and Key Areas for Improvement to Promote Public-private Partnerships
in Infrastructure: Indonesia's perspective. Engineering." Construction and Architectural
Management, 4(2014):383-402. Print.
[2]. Loosemore M, Raftery J, Reilly C, Higgon D. Risk management in projects. Taylor &
Francis, (2006). Print.
[3]. Martinus P. Abednego, Stephen O. Ogunlana. "Good project governance for proper risk
allocation in public private partnerships in Indonesia." International Journal of Project
Management, 24 (2006): 622-634. Print.
[4]. Tiong RLK and Alum J. "Final negotiation in competitive BOT tender." Journal of
Construction Engineering and Management, 1(1997): 6-10. Print.
[5]. Lam KC, Wang D, Lee PTK and Tsang YT. "Modeling risk allocation decision in
construction contracts." International Journal of Project Management, 25(2007): 485-493.
Print.
[6]. Yang, Chao, and Song Li. "Research on Risk Management of Engineering Project Based
on PPP Mode-Taking A Municipal PPP Project as an Example." Journal of
Transportation Finance and Accounting 4(2018): 39-45. Print.
[7]. Li, Xiangyun, LinLuo, and Yajie Wang. "Current status, problems and countermeasures
of PPP mode implementation in water resources projects." Water resources Economy,
5(2019):27-30. Print.
[8]. Akintoye A, Beck M, Hardcastle C. "Public private partnerships: managing risks and
opportunities." Blackwell Science, 4(2008): 28-56. Print.
[9]. Ernest. Effah. Ameyaw, and Albert PC Chan. "Risk ranking and analysis in PPP water
supply infrastructure projects." Facilities, 33(2015): 7-8. Print.
[10]. Yongjian Ke, Shouqing Wang, etal. "Understanding the risks in China's PPP projects:
Ranking of their probability and consequence." Engineering Construction and
Architectural Management, 5(2011):481-496. Print.
[11]. Li B, Akintoye A, Edwards P J, Hardcastle C. "The allocation of risk in PPP/PFI
construction projects in the UK." International Journal of Project Management,
1(2005):25-35. Print.
[12]. Hodge, G. A., Greve C. "Public -Private Partnerships: an international performance
review." Public Administration Review, 3(2007):545-548. Print.
[13]. Grimsey, Darrin, and M. K. Lewis. "Evaluating the risks of public private partnerships
for infrastructure projects." International Journal of Project Management, 2(2002):107-
118. Print.
[14]. A.Ng, Martin Loosemore. "Risk allocation in the private provision of public
infrastructure." International Journal of Project Management, 25(2007): 66-76. Print.
Abstract: The adoption of PPP mode in water resources projects is conducive to solving the defects of
government funds shortage, long life cycle and low management efficiency under the traditional
financing mode. It is an inevitable trend for water resources survey and design enterprises to
participate in PPP projects. From the perspective of water resources survey and design
enterprises, it is pointed out that the risks it faces when participating in PPP projects as private
mainly involve three levels: risks at government level, risks at market level and risks at project
level. The risk list of water resources survey and design enterprises participating in PPP projects
is established, and the risk sharing mechanism is constructed on the basis of analyzing the
influencing objects and imputation objects of various risk factors. The study provides operable
guidance for water resources survey and design enterprises to carry out negotiation of relevant
clauses and smooth operation of the project when participating in PPP projects.
The International Journal of Social Science and Economic Research Inviting Papers/Articles for Upcoming Issue Volume 9 No. 11 November 2024.
Submit your Paper through Online Submission System. Authors also can Send Paper to
submit@ijsser.org If you need any help contact us +91-9753980183